Soon after the opening of our School in 2012, the mobility question was raised and discussed in various forums. For sustainable reasons, APEEEL2’s position has always been to support soft mobility to access our campus.

As Lux2 school buses were frequently late in the mornings due to heavy road traffic, our Parent’s Association and the School initiated discussions with MDDI (Ministère du Développement Durable et des Infrastructures) to improve school bus access to our campus. The initial meetings in 2016 evaluated the needs to develop a project which was first presented to our association in 2017/18. Since then, the project has been delayed for various administrative and ecological reasons. Due to birds’ species living close to our School, a specific environmental procedure was needed, and the decision was made to split the project into 2 phases. Please refer to our communication from November 2021 (https://www.apeeel2.lu/transport-communication-on-start-of-road-works-11-2021/).

On 31/03/22, MDDI confirmed to us that phase 1 of the roadwork could soon finally start. It indeed started during the Easter holidays.

The estimated planning has been designed to minimize the impact on the traffic during school time and peak hours, with the constraint that all work should be completed by next school start in September. There were some traffic issues when leaving the School last Wednesday morning, but they were linked to roadwork at Belle Etoile and not our project.

You will find below an estimated timetable of the planned work until school ends.

  • From 09 until 30/04: At the roundabout.
  • From 02/05: Around CPE, and along the road from Lycée Josy Barthel (LJB) to the roundabout (on LJB’s side).
  • From 01 until 15/06: next to CPE building, enlargement of the parking exit directly on the roundabout to make it double-sided (entry and exit for cars).
  • From 15/06/22: work on the road accessing the School between the roundabout and Lux2’s bus platform. There will be some impact on parking and school access , but hopefully limited until 01/07/22. Between 02/07 and 05/09/22, school access by car will be very difficult.
  • The road work company, selected during the process of the call for tenders for this project, will work 6 days a week to complete a maximum of work before the start of the Luxembourg collective leaves at the end of July. Remaining work including the asphalt overlay will be completed before the School starts on 5 September.

APEEEL2 also requested several times to MDDI to extend our bus platforms to better secure pupils’ access to buses, and increase the number/size of buses when needed. We are pleased to announce our request was accepted, but it is not yet included in the current planning. However, we have received confirmation from MDDI that work will be completed at the latest by the summer 2023.
Phase 2, consisting of creating a new bus exit at the roundabout for a direct access to Route d’Arlon, is currently postponed. It will not be planned until protected birds have migrated to another location which has been foreseen for them.

APEEEL2 has requested MDDI to organize an information meeting to explain the full project to the School community, but we have not received any confirmed date as yet. In the meantime, we can only publish some of the plans to help parents understand better the different work phases.

In the end, eventhough this project will reduce the number of parking spaces available for parents, we expect some significant improvement for pupils and school staff coming to School by bus.

If you have any questions, pleease do not hesitate to contact us and we will do our best to answer you.